General Steps for Interconnection (Non- Certified Based Systems)
Other - General Types of Interconnections
- Non-exporting parallel operation (with paralleling times greater than 100 milliseconds),
- Non-exporting closed transition paralleling (paralleling less than or equal to 100 milliseconds),
- Exporting parallel operation,
- All other paralleling requests.
General Steps:
- Oncor receives a completed Interconnection Application and secures Impact Study Fee (fee schedule included within application
- Oncor prepares and submits to customer an Impact Study or Service Study or
- Oncor secures funding for any required system impacts,
- Oncor schedules and completes any required system changes,
- Oncor reviews customer relay test reports,
- Oncor prepares, submits and secures an Interconnection Agreement from customer,
- Final authorization for operation is granted after the Interconnection Agreement is signed and all the general process items are completed.