General Steps for Interconnection (Non- Certified Based Systems)

Other - General Types of Interconnections

  • Non-exporting parallel operation (with paralleling times greater than 100 milliseconds),
  • Non-exporting closed transition paralleling (paralleling less than or equal to 100 milliseconds),
  • Exporting parallel operation,
  • All other paralleling requests.

General Steps:

  • Oncor receives a completed Interconnection Application and secures Impact Study Fee (fee schedule included within application
  • Oncor prepares and submits to customer an Impact Study or Service Study or
  • Oncor secures funding for any required system impacts,
  • Oncor schedules and completes any required system changes,
  • Oncor reviews customer relay test reports,
  • Oncor prepares, submits and secures an Interconnection Agreement from customer,
  • Final authorization for operation is granted after the Interconnection Agreement is signed and all the general process items are completed.